Getting a Gantt chart out of Trello: timeline views, Power-Ups, and the plan you need

September 23, 2026 ・ Pinateca Editorial

The board works. Cards move, the team knows what is in progress, and nobody has to ask what happened to a task. Then a client asks for a schedule, or a stakeholder wants to know whether the launch date still holds, and a vertical stack of lists cannot answer the question. Kanban shows state. A Gantt chart shows time.

The search usually starts with "trello gantt chart" and ends in one of three places: Trello's own Timeline view, a Power-Up from the directory, or a spreadsheet built by hand from an export. Each of those costs something different, and two of them stop being worth it at a predictable point. This article covers what Trello includes today, what the Power-Up route actually buys, what none of these options give you, and how to decide without paying for a year to find out.

What Trello includes today

Trello has a Timeline view. It is not a Power-Up and it is not an add-on. It is one of the alternative views built into the product, alongside Calendar, Table, Dashboard, and Map.

The important detail is which plan it sits on. As of today, Trello's pricing page lists Board and List views on Free and Standard, and Calendar, Timeline, Table, Dashboard, and Map on Premium and Enterprise. Atlassian's documentation states it plainly: "The Timeline view is only available for boards and Workspaces that are subscribed to Premium and Enterprise."

Plan Price per user per month Views included
Free $0 Board, List
Standard $5 billed annually, $6 billed monthly Board, List
Premium $10 billed annually, $12.50 billed monthly Board, List, Calendar, Timeline, Table, Dashboard, Map
Enterprise $17.50 billed annually Board, List, Calendar, Timeline, Table, Dashboard, Map

For a team of five, Premium is $50 a month billed annually. For a team of twelve, $120. That is the real question behind most searches for a Trello Gantt chart: whether the schedule is worth moving the whole workspace up two plan tiers, given that everyone on the board needs a seat, not just the person who reads the chart.

Trello's Free plan is generous in other respects. It allows up to 10 boards per Workspace, unlimited cards, unlimited Power-Ups per board, and is free for up to 10 collaborators per Workspace. The limit that bites is not storage or card count. It is that the two views most useful for planning, Calendar and Timeline, sit two tiers up.

What Timeline view actually does

Assuming Premium is on the table, it is worth knowing what arrives with it, because the name "Gantt chart" carries expectations that Timeline view does not meet.

Cards become bars on a horizontal date scale. A card with only a due date appears at a point. A card with both a start and an end date stretches across the range, which means the first job after switching the view on is going back through cards and adding start dates that were never needed on a kanban board.

Bars can be dragged and resized directly. The documentation describes clicking and holding the edge of a card to "stretch it and set up new date ranges", so rescheduling happens on the chart rather than card by card.

Grouping is available by list, member, label, or none. Grouping by member is the most useful of these, because it turns the schedule into a workload picture and shows who has three bars overlapping in the same week.

Zoom runs from day through week, month, quarter, and year.

What is not there matters just as much. Trello's Timeline documentation does not describe task dependencies or a critical path. There are no arrows between bars, and moving one bar does not move the ones that follow it. Timeline view is unavailable on mobile.

There is also a setup cost that nobody mentions in the plan comparison. Turning Timeline view on does not produce a schedule. It produces an empty chart with a handful of bars, because a board that has been running as kanban carries due dates and very little else. Someone has to go through the active cards, decide when each piece of work is meant to start, and enter that date. On a board of eighty cards that is a real afternoon, and it is work that has to happen again for every board the team wants on a timeline. Budget for it before judging whether the upgrade paid off, because the first week after switching usually looks worse than the kanban board did.

For many teams the result is still fine. A visual schedule where bars can be dragged answers the client question and the stakeholder question. For teams that plan construction, agency deliverables with hard handoffs, or anything where a slip in one stage must visibly push the next one, the absence of dependency links is the thing that sends them looking again six months later.

The Power-Up route

Trello's directory contains Gantt and scheduling Power-Ups from third parties, and the Free plan allows unlimited Power-Ups per board. That combination looks like a way to skip Premium entirely, and sometimes it is.

The trade-offs are consistent across most of them.

Billing is separate and usually per user. The Power-Up is a product from another company with its own subscription, its own plan tiers, and its own free limits. A team that adds two or three Power-Ups to solve two or three gaps ends up with several small monthly charges and several vendors, which is often more than the Premium seat it was avoiding.

The data lives somewhere else. Most Gantt Power-Ups read your cards and store dependencies, baselines, and other scheduling information on their own servers. That is how they add what Trello does not have. It also means a second company holds project data, a second account to close when someone leaves, and a second thing to check before a security review.

The chart is a panel, not the board. Power-Ups render inside Trello's frame. They work, but the experience is a window into a different product rather than another way of looking at the same cards, and people who were not the one who installed it tend not to open it.

They disappear. Power-Ups get acquired, change pricing, or stop being maintained. When the schedule lives in one, the schedule leaves with it.

The Power-Up route is the right answer in one specific case: when the board is otherwise fine on Free or Standard, one project needs dependency arrows, and the number of people who will actually open the Gantt view is small. It is the wrong answer when the goal is for everyone to see the schedule, because then everyone needs the second product too.

The export and spreadsheet route

The third option is to stop asking Trello for a chart. Export the board to CSV or JSON, drop the cards into a spreadsheet with start and end dates, and draw bars with conditional formatting or a stacked bar chart.

This sounds like a step backwards and is occasionally the right call. A one-page schedule for a client, updated before each monthly meeting, does not need to be live. Building it from a table of dates rather than by hand means updates are edits to numbers, and a spreadsheet costs nothing per seat.

It fails on frequency. The moment dates change more than once a week, someone is spending an hour a week transcribing them, and the chart is wrong between transcriptions. The failure is quiet: nobody announces that the spreadsheet is three weeks old, and decisions get made from it anyway.

A workable compromise is to keep the spreadsheet for the client-facing summary of five to eight stages, and keep the detailed dates on the cards, where the people doing the work maintain them. Copying eight rows once a week is sustainable. Copying eighty is not.

Comparing the three routes

Route Cost Dependencies Stays current by itself Best when
Trello Premium Timeline $10 per user per month billed annually, all seats No Yes Everyone needs to see the schedule and dependencies are not required
Gantt Power-Up Separate per-user subscription from another vendor Usually yes Yes, inside the panel One project needs dependencies and few people will open the chart
Export to spreadsheet Free Manual No A summary for a client, updated on a fixed rhythm

Read that table against how the schedule will be used, not against the price. A schedule nobody opens is expensive at any price, and a schedule that is always three weeks out of date is worse than no schedule, because it is believed.

When the answer is a different tool

There is a fourth option that most comparison articles skip, and it is worth naming because the arithmetic sometimes favors it clearly.

The reason a Gantt chart is hard to get out of Trello is structural rather than accidental. Trello is a kanban product. Everything else is a view layered on top of that, which is why start dates are optional, why Timeline sits on an upper plan, and why dependencies were never part of the model. Tools built with multiple board types from the start treat the Gantt board as a first-class citizen rather than a premium rendering of a kanban board.

The questions worth asking before switching are practical ones.

  • Does the Gantt or timeline view come with the plan the whole team will actually be on, or is it the reason to upgrade?
  • Do cards carry both a start date and an end date without extra setup?
  • Can the same cards be seen as a board, a list, and a calendar, so that people who prefer kanban keep the dates current without opening the Gantt view?
  • Can people outside the team look at the schedule without a paid seat?
  • Is there a supported import path, so the boards do not have to be rebuilt by hand?

That last one decides whether switching is a weekend or a quarter. Trello exposes board data through its API and its export, so most tools that support importing from Trello can carry lists, cards, descriptions, labels, and due dates across. Checking exactly which fields survive before committing is worth an afternoon. Attachments, comments, and custom fields are the ones that most often do not.

A direct comparison of Pinateca and Trello covers where the two differ on views, seats, and pricing tiers, and the features page shows how kanban, Gantt, calendar, and timetable boards work against the same cards.

What to change first

Before paying for anything, spend twenty minutes adding start dates to the cards on one active board. Most Trello boards only carry due dates, and without start dates every Gantt option, built in or not, will draw a row of points rather than a schedule. Once the dates are there, the choice between Premium, a Power-Up, and a tool where the Gantt board is included from the start becomes a question with a visible answer instead of a guess. If the seat count is what is stopping the upgrade, compare it against plans such as Pinateca where all board types are on the free tier.

Q1. Does Trello have a built-in Gantt chart?

Trello has a Timeline view that shows cards as bars on a date scale, which covers most of what people want from a Gantt chart. It requires Premium or Enterprise. Trello's documentation does not describe task dependencies or a critical path in Timeline view, so it is closer to a visual schedule than a full Gantt chart.

Q2. Which Trello plan do I need for Timeline view?

Premium or Enterprise. Trello's pricing page lists Board and List views on Free and Standard, and Calendar, Timeline, Table, Dashboard, and Map on Premium and Enterprise. Premium is $10 per user per month billed annually, or $12.50 billed monthly. Every member of the Workspace needs a seat, not only the people who view the chart.

Q3. Can I get a Gantt chart on Trello's free plan?

Not through Trello's own views, because Timeline is a Premium feature. The Free plan does allow unlimited Power-Ups per board, so a third-party Gantt Power-Up is possible. Those are separate products with their own subscriptions and their own free limits, and they store your scheduling data on their servers.

Q4. Why do my Trello cards show as single points instead of bars?

Because those cards only have a due date. Trello's Timeline view stretches a card into a bar when it has both a start date and an end date, which are set while editing the card's due date. Boards that grew as kanban usually have due dates only, so adding start dates is the first step before any Gantt view is useful.

Q5. Can Trello show dependencies between tasks?

Trello's Timeline documentation does not mention dependencies or critical path, and moving one bar does not shift the ones that follow it. Teams that need dependency arrows generally add a third-party Power-Up that stores those links itself, or move to a tool that models dependencies natively.

Q6. Is it worth exporting Trello to a spreadsheet instead?

For a client-facing summary of five to eight stages updated on a fixed rhythm, yes. Build the chart from a table of dates so updating means editing numbers. It stops being worth it when dates change more than once a week, because the spreadsheet is then wrong most of the time and nobody announces it.